鈥斅犅4 min read
Construction Purchase Order 101: Your Ultimate Guide to PO
Last Updated Mar 26, 2025
Last Updated Mar 26, 2025

Construction purchase orders are key financial elements of an overall project contract. In construction specifically, a purchase order (PO) is typically validated by two parties: the buyer and seller. The buyer (usually an owner or main contractor) issues a PO to the seller (usually a main contractor or speciality contractor) to cover the cost of the project.
The document outlines the price and quantity of goods or services necessary to complete the project contract as agreed upon by both parties.
Table of contents
Information in a Construction Purchase Order
In order to illustrate the contents of a construction purchase order and how they are relevant to the completion of a project, let鈥檚 use a hypothetical scenario featuring Jane and John. Let鈥檚 say Jane is a project manager for a main contractor (MC) hired to build a warehouse, while John is a concrete contractor who won the tender to pour the foundation of that warehouse.
Description of Deliverables
Upon receiving the tender for the concrete pour, John and his team visit the site. They identify the tools, equipment, materials and labour needed to complete the project. Once he relays that information to the MC, Jane鈥檚 team will draft a PO for the deliverables outlined by John and his team.
Number of Deliverables
As Jane鈥檚 team is drafting the PO, they have to be diligent with listing the quantities for each deliverable provided by John. This is important because a PO explicitly states the MC鈥檚 fiscal responsibility for the deliverables needed to complete the work expected of the speciality contractor. This document, therefore, protects both parties by ensuring that:
- The MC receives the amount and quality of work requested.
- The SC gets paid for the items needed to complete the work requested.
Agreed-Upon Cost
As Jane鈥檚 team lays out the itemised list of deliverables requested by John鈥檚 team, the two parties will agree on a cost per item and possible discounts for certain quantities of those items.
Terms of Payment
The terms of payment for a construction purchase order are usually based on credit. The MC sends the PO to the SC to request a service on credit. This protects the MC in the event that payment is given before the completion of the project.
The terms of payment can also be set in regards to a net payment term. It defines how many days after a payment application is submitted the buyer has to make the payment. In this scenario, we will say that Jane approves a PO with a net 30 term, which means John will be paid within 30 days of submitting a payment application for the completed work.
Due Dates
Now that the parties have agreed to the terms of payment, Jane and Johns鈥 teams will decide on due dates for the deliverables requested in the PO. These dates will inform the date of delivery of those deliverables.
Method of Delivery
One of John鈥檚 deliverables in the PO is an extra concrete mixer that has to be shipped from out of the county. The delivery method for that mixer will typically be defined as one of two FOB (Free On Board) shipping terms: FOB Shipping Point (or FOB Origin) and FOB Destination. If 鈥淔OB Origin鈥 is agreed upon, the MC will become responsible for any loss or damages incurred to the mixer as soon as it leaves the warehouse and is in transit to the job site. If 鈥淔OB Destination鈥 is agreed upon, the SC will be responsible for any damage incurred to the mixer until it reaches the job site.
Reference Numbers
The reference number is one of the most important pieces of the construction purchase order鈥攊t helps track the document. Since a project can have hundreds of PO鈥檚 attached to it, they can commonly become lost or jumbled during a project鈥檚 lifetime. The only way to prove that a service or material was completed or delivered as requested is to be able to locate the respective PO by its reference number.
Shape the Future of the Built Environment at 麻豆视频's Construction Summit
Engage with construction leaders and discover the latest technology and best practices that are driving change across the industry.

Purchase Order vs Payment Application
There is one main difference between a construction purchase order and a payment application: A PO is submitted by the buyer (Jane the MC) to determine the cost of a contract before the work is completed. In contrast, a payment application is submitted by the seller (John the SC) after the work is completed to receive an agreed-upon payment.
Construction PO vs Contract
The difference between a construction purchase order and a contract is that a contract is a legally binding document that covers products, agreed prices and payment terms, and conditions for the entirety of a construction project. It includes all necessary purchase orders (documents that outline the price and quantity of goods or services necessary to complete the project contract) and payment applications.
Final Tips for Drafting a PO
A construction purchase order is a key item in a project contract because it鈥檚 a legally binding document that protects both the buyer and seller of a product or service. When drafting a PO, it鈥檚 important to remember to be explicit and detailed when filling out the following sections:
- Description of deliverables
- Number (or quantity) of deliverables
- Agreed-upon cost
- Terms of payment
- Due dates
- Method of delivery
- Reference Numbers
Categories:
Tags:
Written by
Tom Noctor
16 articles
Having worked in construction for many years both on the ground as an electrician and in the design space in roles such as BIM Manager, I witnessed the highly inefficient operations of our industry and also the amount of waste generated from project delivery. I am a Digital Construction Technologies advocate @麻豆视频 Technologies, supporting and guiding the construction industry in adopting/utilising technology to deliver projects in a lean sustainable manner.
View profileExplore more helpful resources

Construction Procurement Strategy, Methods and Processes
Every successful construction project depends on securing the right materials, labour, and services at precisely the right time and cost. Procurement serves as the engine that drives this coordination, quietly...

Construction Site Signage: What to Use and Where to Place It
Clear, consistent signage on construction sites serves a vital purpose 鈥 it meets legal requirements and provides frontline defence against risks, ensuring everyone’s safety. From alerting workers to hazards to...

Building a Culture of Process Excellence in Construction
Process excellence delivers significant efficiency gains for construction companies by helping them deconstruct and rebuild internal business and project processes to maximise time and cost efficiency. This article explains what...

Digital Twins in Construction: Benefits, Uses and Challenges
Construction is entering a new era driven by data, connectivity, artificial intelligence, and digital precision. At the forefront of this transformation are digital twins: advanced replicas of real-world assets that...